Melbourne Arts Precinct Transformation (MAPT) – State Theatre, Arts Centre Melbourne

Services: Design, Engineering, Installation

Client: Lendlease

Location: Melbourne, VIC

The Melbourne Arts Precinct Transformation (MAPT) State Theatre redevelopment was a major brownfield project within Arts Centre Melbourne, modernising one of Australia’s most iconic performing arts venues while preserving its distinctive heritage features.

Fredon delivered both the electrical and technology packages, working within a live and operational cultural precinct. The electrical scope covered the design development, supply, installation, testing, commissioning, certification and handover of power, lighting, communications, security and supporting high-voltage services across six separable portions.

The State Theatre works involved a significant strip-out and rebuild of the existing electrical infrastructure, including new and modified power distribution, main switchboards and distribution boards, emergency and exit lighting, cable reticulation, undercroft services and specialist theatre systems. The project also incorporated complex HV infrastructure, including 11kV feeders, switchgear, protection, earthing and interlocking, with the network connecting the wider Arts Centre Melbourne precinct, including the National Gallery of Victoria, Hamer Hall and Sidney Myer.

Delivering the electrical works within the existing heritage building presented significant challenges. Ceilings, walls, floors and sections of carpet were protected, while existing services required careful investigation and coordination to identify and work around. Extensive tracing, identification and verification were required before demolition could proceed.

Fredon Technology delivered the State Theatre’s Stage Lighting and Audio-Visual infrastructure, including approximately 190 kilometres of cabling, 3,355 tested tie lines, more than 8,300 terminated connections, 715 engraved interface panels and 25 equipment racks. The scope also included lighting control infrastructure, technical communications, performance networking and integration with specialist theatre systems.

A major technology feature was the installation and commissioning of a large-scale d&b Soundscape immersive audio system, comprising approximately 200 loudspeakers, 60 amplifiers and primary and secondary Milan audio networks. Many of the loudspeakers were concealed within the theatre’s heritage architectural linings, requiring custom framing, bracketry and extensive on-site adjustment to achieve the required acoustic performance.

The project required close collaboration between Fredon’s engineering, project management and site teams to overcome concealed conditions, restricted access, transmission-distance limitations, voltage-drop requirements and containment constraints. Specialist lighting solutions were also developed to balance modern theatre performance with the architectural requirements of the heritage venue.

One of the project’s most significant challenges was the coordination of major electrical outages. Fredon helped plan the first full-site de-energisation of its kind across the precinct in 40 years, carefully coordinating temporary supplies, theatre operations, NGV environmental controls and the wider precinct’s requirements.

Comprehensive testing and commissioning ensured the completed systems were proven and operationally ready. The Technology scope included nine formal witness-testing sessions and 13 client-training sessions, equipping Arts Centre Melbourne’s operational and technical teams to confidently operate and maintain the new systems.

Through technical expertise, collaborative delivery and innovative engineering, Fredon successfully delivered a future-ready electrical and technology solution within a complex, live and heritage-sensitive environment.

The project was recognised with the 2026 Major Project Award at the annual Fredon Conference, acknowledging the exceptional technical complexity, collaboration, innovation and delivery achieved by the Fredon team.